Solar Park Costs On The Rise In India

News

Solar parks are a vital piece to India’s solar future and were designed to reduce bottlenecks and bring down large-scale project development costs by allocating land and providing transmission infrastructure, big challenges for solar project development in India. The government recently doubled down and increased the proposed solar park capacity from 20 GW to 40 GW and is providing financial support to the tune of Rs.81 billion (~$1.23 billion) in Central Financial Assistance (CFA) and $100 million (~Rs.6.5 billion) from the World Bank.

While solar parks have played an important role in lowering tariffs in recently conducted reverse auctions, our research is finding that costs are actually increasing, squeezing the margins even more in a highly competitive auction market. Most of the developers have told Mercom that incomplete solar park infrastructure, exorbitant upfront fees, and not so transparent yearly charges are all adding to project costs with some developers calling for auctions outside of solar parks as they think it could be cheaper in some instances.

Even though all solar parks come under the same policy (solar parks are being developed in collaboration with state governments with Solar Energy Corporation of India (SECI) as the implementing agency), each solar park has a different fee structure which is leading to the varying in tariffs and project costs. In fact, two solar parks in the same state can have different fees. According to Mercom’s data, the solar park fee in India varies from Rs.3.73 million (~$58,039)/MW in Karnataka to Rs.10.58 million (~$164,335)/MW in Gujarat.

Land application fees (non-refundable one-time), upfront development charges (one-time), annual leases of land, and annual operation and maintenance (O&M) charges are the most common park fees or charges. However, developers are faced with differing stamp duties in each state and service taxes on all components. “Hidden charges end up inflating project costs," commented one developer.

In each state or even in different areas in the same state, the topography and solar irradiation changes, and the distance from the substation also changes; all these lead to differences in park fees, stated a SECI official. If the park development agency or authority is spending more on construction of transmission infrastructure, land acquisition and levelling - it will obviously charge more, added the SECI official.

In response, developers said they understood that land lease charges and development charges can vary, but they were skeptical as to why operation and maintenance charges vary across states. That is an area they see where SECI or the implementing agency can make a change.

Fenix Reach 150,000 Zambians In Nine Months
NREL Cuts Cost Of III-V Tandem Cells
First “plug And Play” Power-enhancing Ribbons For PV Interconnection
BayWa R.e. Receives The National Energy Globe Award For Its Solar Project In Zambia
InnoEnergy Start-ups Have Created 1,741 Jobs
Strong Solar Performance Triggers Record Low Fossil Fuel Generation In Third Quarter
Trina Solar Supplies Modules To Ukraine's Largest Solar Power Plant
Trina Solar Supplies Modules To Ukraine's Largest Solar Power Plant
Welsh Researchers Supersize Perovskite Solar Technology
ABB Connects Sweden´s Largest Solar Park To The Grid
Ensibo Adopts QOS O&M Software To Manage Of 120 MW PV Portfolio
Organic Solar Hits New Landmark
The Time To Invest In Emission Control And Renewable Energy Is Now
BYD And KOSTAL Announce Strategic Partnership For Energy Storage Solutions
SMA Surpasses 1 GW Installed Solar In Latin America
Solar Might Become EU’s Fastest-Growing Energy Source Due To Elimination Of Tariffs
Spottitt Launches Cloud-Based Geospatial Data Analysis On DNV GL’s Veracity Platform
BayWa R.e. Partners With Mexico’s Largest Distributor Of PV Products
REDEN Solar Completes The Refinancing Of Its Iberian Solar PV Assets
RES And VBB Celebrate Construction Progress Of 10 MW Storage Project
K-Space Grows In-line Metrology Revenue
Amarenco France's Number One In Rooftop Solar After Latest Tender Results
New III-V Device Concept Combines Two Structures
World Bank To Invest $1 Billion Towards Battery Storage

Info
×
Search the news archive

To close this popup you can press escape or click the close icon.
Logo
×
Logo
×
Register - Step 1

You may choose to subscribe to the Solar + Power Magazine, the Solar + Power Newsletter, or both. You may also request additional information if required, before submitting your application.


Please subscribe me to:

 

You chose the industry type of "Other"

Please enter the industry that you work in:
Please enter the industry that you work in:
 
X
Info
X
Info