First Solar To Commence CdTe Module Installation At AV Solar Ranch One



The Los Angeles County Department of Public Works and First Solar have reached an agreement on the installation of solar modules at the Solar Ranch One photovoltaic (PV) power plant currently under construction in the Antelope Valley.

The agreement enables First Solar to continue construction activities of the 230 MW power plant. Installation of the modules had been delayed while First Solar and Public Works worked to achieve agreement related to the module code certifications.

Dennis Hunter, Deputy Director of County Public Works, said the Department was responsible for ensuring that all applicable building codes were met by the project in order to protect the health and safety of county residents.

"We're pleased to see the project back on track," Hunter said. "Following our discussions, we are now confident in First Solar's ability to meet our health and safety requirements."

Work on the project began in August 2011 and is creating about 400 jobs during construction on the 2100 acre site.

Los Angeles County Supervisor Michael D. Antonovich said the AV Solar Ranch was one of the largest construction projects currently underway in the county and provided significant employment opportunities to the Antelope Valley community.

"I am very pleased my office was able to facilitate resolution that helped towards finally resolving the permit issue involving the safety requirements of the AVSR1 project in the Antelope Valley," Supervisor Antonovich said. "More importantly, this resolution will help those employees that have been furloughed to return to work as quickly as possible."

Jim Lamon, First Solar Senior Vice President of Engineering, Procurement and Construction and Operations and Maintenance, said the company greatly appreciates the collaboration and commitment from Public Works and 5th District staff to approve the module installation plan.

"As the first utility-scale solar PV project in Los Angeles County, this was the county's first opportunity to apply its codes to a facility of this magnitude, which required significant time and effort for everyone involved," Lamon said. "After a very collaborative process, we are confident we have the county's support to keep the project moving to completion, and that this process has paved the way for future projects in the region, which has great potential for solar energy production."

First Solar expects to ramp up staffing for the project over the next several weeks.

Solar Energy For Water Treatment: IBC SOLAR Helps Water Authority Become More Sustainable
SunBrush Mobil And Infinity Establish Service Base At Benban, Africa's Largest Solar Park
Driving Efficiency Through Flexible Solar Power Solutions
Sonnedix Brings Chile Closer To Meet Its Renewable Power Targets
Q CELLS Solar Modules Keeping The Lights On For Dutch Bulb Grower
Oakapple Renewable Energy Appoint Stuart Gentry To Head Business Development
Going Green In Lancashire – Hundreds Of Houses Installed With Solar Panels In Ground-breaking Project
SolarArise Commissions 75 MW Solar Plant In Uttar Pradesh
Analysis Of UK Commercial Roof Space Shows Solar PV Film Can Achieve Net Zero Without Greenfield Sites
Luxcara And GE Renewable To Deliver 753 MW To Sweden With Single Onshore Wind Farm
Winch Energy Closes Largest Mini Grid Financing Portfolio To Date
US Solar Fund To Acquire Up To 50% Of 200MWDC Mount Signal 2
AEG Power Solutions Equips The Microgrid Laboratory Emulator Of Paderborn University
BayWa R.e. And HeidelbergCement Sign First Solar Corporate PPA In Polish History
The Smarter E South America Postponed To October 18-20, 2021
Leclanché Selected By ENERGODATA To Provide Battery Storage
Sonnedix Adds 40 MW Of Capacity To Its Portfolio In Chile
SUNfarming Reaches Financial Close On Project Financing For 26 MWp PV Portfolio In Poland
VivoPower International PLC Announces Completion Of Electrical Works For 39 MWdc Molong Solar Farm
Greencoat Renewables Announces First Transaction In Nordic Market
Ib Vogt Achieves Financial Close And Start Of Construction Of 116 MWp Solar PV Project In Malaysia
SUNfarming Secures EUR 10 Million In Fresh Money For Poland
International Solar Alliance Special Assembly Elects Dr Ajay Mathur As New Director General
Sonnedix Acquires 150MW Utility Scale Project Located In Central Chile

×
Search the news archive

To close this popup you can press escape or click the close icon.
Logo
×
Logo
×
Register - Step 1

You may choose to subscribe to the Solar + Power Magazine, the Solar + Power Newsletter, or both. You may also request additional information if required, before submitting your application.


Please subscribe me to:

 

You chose the industry type of "Other"

Please enter the industry that you work in:
Please enter the industry that you work in:
 
X
Info
X
Info
{taasPodcastNotification} Array
Live Event