News Article

Etrion, Announces Agreement With ABB, To Complete 10 MW Solar Project

News
Deal in place following Italian government clarification of incentives
Marco Northland, Etrion's CEO, commented, "We are pleased to engage ABB to proceed with our 10 MW project under construction following the recent Italian government decree clarifying incentives for new solar projects. Based on the new feed-in-tariff and the reduced contractor cost, we expect to maintain our original projected internal rate of return for this project."

The Helios ITA 3 project includes two 5 MW ground-mounted solar PV parks under construction, Brindisi and Mesagne, in the Puglia region of Italy. Construction of the project was voluntarily delayed in order to clarify the Italian feed-in-tariff applicable to projects connected after May 31, 2011. On May 5, 2011, the Italian government approved a decree establishing tariffs for new solar PV plants, and Etrion subsequently decided to proceed with ABB as the new contractor.

Construction of the Helios ITA 3 parks is expected to be completed by August 31, 2011. The first electricity sales from the project under the Italian feed-in-tariff regime are expected during the fourth quarter of 2011.

The Helios ITA 3 parks are expected to receive a feed-in-tariff of EUR0.25 per kilowatt-hour (kWh) plus the market price of approximately EUR0.08 per kWh. The Italian feed-in-tariff guarantees the purchase price for solar electricity by the Italian government for 20 years from the start of operations.

The 10 MW project is expected to produce 16.8 million kWh of electricity and EUR4.6 million of earnings to Etrion before interest, taxes, depreciation and amortization (EBITDA) per year.

In order to accelerate construction of the Helios ITA 3 project, Etrion has received a bridge loan of EUR28 million from the Company's major shareholder, the Lundin family. The bridge loan is interest-free and will mature one year after draw down. Etrion expects to repay the bridge loan upon final draw down of the project's existing non-recourse loan facility with Natixis, WestLB and Mediocreval following grid connection of the Helios ITA 3 solar parks. In consideration for providing the bridge loan, Etrion has issued 6.5 million common shares of the Company to Lundin family trusts.
VivoPower International PLC Announces Completion Of Electrical Works For 39 MWdc Molong Solar Farm
AEG Power Solutions Equips The Microgrid Laboratory Emulator Of Paderborn University
Sonnedix Acquires 150MW Utility Scale Project Located In Central Chile
Oakapple Renewable Energy Appoint Stuart Gentry To Head Business Development
Driving Efficiency Through Flexible Solar Power Solutions
SUNfarming Secures EUR 10 Million In Fresh Money For Poland
Ib Vogt Achieves Financial Close And Start Of Construction Of 116 MWp Solar PV Project In Malaysia
Sonnedix Adds 40 MW Of Capacity To Its Portfolio In Chile
International Solar Alliance Special Assembly Elects Dr Ajay Mathur As New Director General
SUNfarming Reaches Financial Close On Project Financing For 26 MWp PV Portfolio In Poland
Sonnedix Brings Chile Closer To Meet Its Renewable Power Targets
Greencoat Renewables Announces First Transaction In Nordic Market
Solar Energy For Water Treatment: IBC SOLAR Helps Water Authority Become More Sustainable
Q CELLS Solar Modules Keeping The Lights On For Dutch Bulb Grower
SunBrush Mobil And Infinity Establish Service Base At Benban, Africa's Largest Solar Park
SolarArise Commissions 75 MW Solar Plant In Uttar Pradesh
BayWa R.e. And HeidelbergCement Sign First Solar Corporate PPA In Polish History
Going Green In Lancashire – Hundreds Of Houses Installed With Solar Panels In Ground-breaking Project
Luxcara And GE Renewable To Deliver 753 MW To Sweden With Single Onshore Wind Farm
Analysis Of UK Commercial Roof Space Shows Solar PV Film Can Achieve Net Zero Without Greenfield Sites
Winch Energy Closes Largest Mini Grid Financing Portfolio To Date
Leclanché Selected By ENERGODATA To Provide Battery Storage
US Solar Fund To Acquire Up To 50% Of 200MWDC Mount Signal 2
The Smarter E South America Postponed To October 18-20, 2021

×
Search the news archive

To close this popup you can press escape or click the close icon.
Logo
×
Logo
×
Register - Step 1

You may choose to subscribe to the Solar + Power Magazine, the Solar + Power Newsletter, or both. You may also request additional information if required, before submitting your application.


Please subscribe me to:

 

You chose the industry type of "Other"

Please enter the industry that you work in:
Please enter the industry that you work in:
 
X
Info
X
Info
{taasPodcastNotification} Array
Live Event